From 2022–2024 electricity prices in Pakistan rose by nearly 100%. Since then, they have further jacked up by another 45%, with the current base tariff for high‑tier domestic consumers (>700 units) now standing at PKR 57–58 per kWh. The root cause lies in the capacity charges paid to IPPs and the pressure of IMF programs to reduce subsidies. Pakistan’s electricity paradox is therefore not about a shortage of installed capacity but about underutilization and the way idle charges are passed on to consumers. Installed capacity in 2026 stands at around 46,600 MW, which translates to approximately 408 TWh annually, if fully utilized. Yet actual consumption is only close to 127.5 TWh, meaning system‑wide utilization is stuck at max 31%. This forces the government to pay IPPs about PKR 1.4 trillion annually for unused capacity, inflating tariffs to unsustainable levels.
It is important to clarify what this 31% utilization means.
Out of the total installed potential of 408 TWh, IPPs are contributing about
20% of that potential, while hydro and nuclear together provide the remaining 10–11%.
In other words, IPPs themselves are running at 35–40% of their own installed
capacity.
If Pakistan were to achieve full utilization across all
sources i.e. IPPs, hydro, and nuclear, tariffs could realistically fall to PKR
14–18 per kWh. Even at with 60–70% combined utilization, tariffs could drop to
PKR 16–22, providing meaningful relief. Importantly, if we consider a scenario
of 100% utilization without hydro or nuclear, relying only on IPPs, tariffs will
still fall compared to today because idle capacity charges vanish. In that
case, costs would be higher than the balanced mix but still substantially lower
than current tariffs, landing around PKR 17–20 per kWh.
When we add up the realistic contributions with IPPs at 100%
(408 TWh), hydro at 30% (122 TWh), and nuclear at 10% (41 TWh), the total
billable electricity potential reaches around 571 TWh annually. This is more
than four times current consumption. At that level, idle charges disappear,
fixed costs are spread across a much larger base and tariffs settle in the PKR
14–18 range.
Cheaper electricity will substitute for other fuels. Domestic
piped gas remains cheaper at PKR 4–5 per kWh equivalent, but electricity at PKR
14–18 becomes competitive against imported LNG (PKR 18–22) and cheaper than LPG
(PKR 20–25). This means those relying on LPG cylinders would immediately
benefit from switching to electricity, while industry dependent on LNG would
find electricity a viable alternative.
The conclusion is straightforward: Pakistan must begin by
lowering electricity tariffs. Cheaper tariffs will encourage households and
industry to consume more power, reducing theft and shifting demand back to the
grid. The government may have to absorb some fiscal pressure initially, but as
utilization rises, idle capacity charges disappear, creating a cycle of
affordability and competitiveness. With ~571 TWh of billable electricity
available, tariffs can be brought down to PKR 14–18 per kWh, LPG users can enjoy
cheaper energy, and industry can gain a decisive edge against imported fuels.
Excess electricity at cheaper rates will also spur technological development,
while villages that currently see no prospect of electrification for decades
can finally be connected to the grid.
|
Scenario |
Units Billed (TWh) |
Idle Capacity Charges |
Hydro/Nuclear Share |
IPP Share (within mix) |
Losses Impact |
Base Tariff (PKR/kWh) |
Total Available Billable Units |
|
Current (31% utilization) |
127.5 |
PKR 11–12 |
30% hydro, 10% nuclear |
20% of system potential (90–95 TWh) |
PKR 4–5 |
57–58 |
127.5 TWh |
|
60% Utilization (combined mix) |
245 |
PKR 4–5 |
30% hydro, 10% nuclear |
~50% of system potential (~200 TWh) |
PKR 2–3 |
18–22 |
245 TWh |
|
70% Utilization (combined mix) |
286 |
PKR 2–3 |
30% hydro, 10% nuclear |
55% of system potential (225 TWh) |
PKR 2–3 |
16–20 |
286 TWh |
|
100% Utilization (all sources) |
408 |
PKR 0 |
30% hydro, 10% nuclear |
60% of system potential (245 TWh) |
PKR 2–3 |
14–18 |
408 TWh |
|
100% Utilization (IPP‑only) |
408 |
PKR 0 |
0% hydro, 0% nuclear |
100% IPPs (~408 TWh) |
PKR 2–3 |
17–20 |
408 TWh |
|
Total Billable Units (IPPs 100%, Hydro 30%, Nuclear 10) |
— |
PKR 0 |
30% hydro, 10% nuclear |
100% IPPs (~408 TWh) |
PKR 2–3 |
14–18 |
571 TWh |
References
- NEPRA
Tariff Notifications (2022–2024) — Ministry of Energy (Power
Division), Government of Pakistan.
- July
2022 hike (+7.91 Rs/unit)
- July
2023 hike (+7.50 Rs/unit + surcharge)
- July
2024 hike (+7.12 Rs/unit)
- NEPRA
Domestic Tariff Slabs (2026) — Current base tariff schedule showing
>700 units slab at PKR 57–58 per kWh (exclusive of taxes).
- NEPRA
State of Industry Report 2023 — Installed generation capacity
breakdown: Hydro 27%, Nuclear 8%, Thermal IPPs 43%, Renewables 7%. Total 43,513
MW.
- Renewables
First – Pakistan Electricity Review 2025 — Installed capacity 46.2 GW,
generation 137 TWh, capacity payments
- IMF
Country Report (2024–25) — Notes on subsidy withdrawal, circular debt and
tariff escalation pressures.
- Private
Power & Infrastructure Board (PPIB) — Portfolio of hydro and coal
projects, confirming hydro/nuclear expansion pipeline.